Limestone Networks - DFW1 Core Upgrades – Maintenance details

All systems operational

DFW1 Core Upgrades

Completed
Scheduled for July 02, 2025 at 5:00 AM – 10:16 AM

Affects

Service Regions

Under maintenance from 5:00 AM to 10:16 AM

DFW - Dallas, TX

Under maintenance from 5:00 AM to 10:16 AM

Updates
  • Completed
    July 02, 2025 at 10:16 AM
    Completed
    July 02, 2025 at 10:16 AM
    Maintenance has completed successfully.
  • Update
    July 02, 2025 at 6:00 AM
    In progress
    July 02, 2025 at 6:00 AM

    The first core replacement has been successfully completed. Work to bring down and replace the second and final core is now underway.

  • In progress
    July 02, 2025 at 5:00 AM
    In progress
    July 02, 2025 at 5:00 AM

    Scheduled maintenance is now underway.

  • Planned
    July 02, 2025 at 5:00 AM
    Planned
    July 02, 2025 at 5:00 AM

    We will be performing a maintenance window to upgrade a pair of core network routers at our DFW1 facility. This upgrade will enhance our infrastructure to support additional 100Gbps port capacity.

    During the maintenance, customers may experience brief intermittent packet loss or increased latency as routes transition to the new core switch pair. We will take every possible measure to minimize any disruption.

    Note: The upgrade will only impact a portion of our DFW1 network. Clients who are directly affected by this maintenance have been notified via email.